Documents Required for New Connection ;

Estimated time and Process:

01.

Application

02.

Feasibility Fee

03.

Feasibility Study

04.

Electricity Plan

05.

Staking & Approval

06.

Construction Cost

07.

Contract

08.

Line Construction

09.

Internal Wiring

10.

Wiring Inspection

11.

Deposit

12.

CMO Preparation

13.

Consumer Connection

 

 

 

 

* Estimated time to complete the total process is 30 days.

 

Following documents should be submitted with the application for new connection:

·       2 (two) copies passport size photograph of the applicant;

·       Certified copy of Land Ownership Documents;

·       Certified design of premises approved by Union Parisad or City Corporation along with  Nam-Jari, Holding Number, Dag Number, Khatian Number, or Chairman/Commissioner Certificate (if design is not approved);

·       Required necessary Electric Load;

·       Certified copy of Rent/Lease Agreement of Premises (if applicable);

·       Certified copy of Owners approval, in case of rental premises;

·       If there are any previous connection, description of previous connection and copy of last paid bill;

·       Description of Temporary Connection (if applicable);

·       Trade License (if applicable);

·       Direction Design of Connection Place;

·       Proper approval of the concerned authority for Industry (Like, Forestry Department,

·       BSTI, Local Administration, etc.);

·       Implementaion of Power Factor Improvement Plant (for Industry);

·       Service Line Length will not be more for 105-feet for premitive house & 110-feet for Building;

·       Certified copy of Contract Agreement between builder and flat-owner of High-rise residential/commercial building.